Working Days Calculator
Enter your numbers and click Calculate — the result updates as you type.
Enter two dates and this calculator counts the working days between them — Monday to Friday only, with weekends excluded and any public holidays you enter deducted.
Result
—
Formula
Worked example
Here is the calculation step by step, using the default values in the calculator above:
- Start: Monday 30 November 2026
- End: Friday 4 December 2026
- Calendar days: 5
- Weekend days: 0
- Working days: 5 − 0 public holidays = 5 working days
Answer: 5 working days
How to use this calculator
- Enter the start date and the end date.
- Enter any public holidays that fall on weekdays in the range — enter 0 if there are none.
- Read the working days, with the calendar days and weekend days underneath.
What the results mean
Working days are the days work normally happens: Monday to Friday. The count includes both the start and the end date, so a single Monday is 1 working day, and a Monday-to-Friday week is 5. Public holidays are deducted because they are weekdays on which no work happens — but only enter holidays that fall on weekdays, since weekend days are already excluded.
Practical uses
- Counting business days for a deadline or delivery.
- Working out how many days of annual leave a holiday uses.
- Planning a project timeline in working days.
- Checking a notice period that counts in working days.
Frequently asked questions
What counts as a working day?
Monday to Friday, excluding public holidays. Saturdays and Sundays are never working days in this calculator.
Does the count include the start and end dates?
Yes. A range from Monday to Friday is 5 working days, and a single weekday on its own is 1 working day.
How do I handle public holidays?
Enter the number of public holidays that fall on weekdays in your date range. Do not count holidays that fall on a weekend — those days are already excluded.
What if a public holiday falls on a weekend?
Do not enter it. Weekend days are excluded automatically, so counting it would deduct it twice.
Can I use this for a notice period?
Yes — enter the first and last dates of the period. If your contract counts working days differently, for example including Saturdays, check the wording before relying on the result.